Contact Us FAQ Sietmap Login
   Home English Home  
8  SUN  2010  -  6: 13
 
About us
China at a Glance
What we do
Where we operate
Documents
Legal instruments
Biddings
News
Gallery
Links
Programmes' Implementation Unit
Shengsha Commercial Mansion
16, Dong San Huan BeiLu
100026 Beijing, China
Tel: +86(0) 10-65950199
Fax: +86(0) 10-65950610
 
What we do
Programmes
  1. Cultural Heritage
  2. Environment
  3. Health
Procurement
  • Environment
  • Procurement Procedures for the Programme "Environmental Programme"

    Introduction

    This section is addressed to end-users in charge of carrying out projects in the environmental sector financed through soft loan by the Italian Government. The main purpose of this section is to describe the procurement principles contained in the Memorandum of Understanding (MOU) of the Programme ¡°Environmental Programme¡± signed by the Italian Ministry of Affairs/Directorate-General for Development Cooperation (DGCS) and the Chinese Ministry of Finance (MOF) in 2006.

    Procurement and Tendering

    In accordance with MOU, contract may be awarded the either through International Competitive Tendering (ICT) or through Local Competitive Tendering (LCT). The choice between local or international tendering lies in the specific characteristics of each project and will be decided during the preparation of Feasibility Study.In case o ICT, the procurement procedures to be followed are those of the European Union or the ones applied for World Bank financed projects in China. In case o LCT, the procurement procedures to be followed are those of the People¡¯s Republic of China (PRC). Any discrepancies occur between the PRC procedures and MOU, what states in MOU shall prevail.

    Goods, Services and Works.

    In case of ICT can be procured goods and services. Works are not eligible for ICT.
    In case of LCT can be procured goods, services and works.

    Standard Bidding Documents for ICT

    The Bidding Documents to be adopted for International Competitive Tendering are:

      • Goods: In case of procurement of goods, end-users and procurement agents will be provided with a Standard Model of Bidding Documents approved by DGCS and MOF. These documents are based on the Standard Bidding Documents for goods of the World Bank applied for China, adapted to be in compliance with MOU.
      • Services: For services, the standard bidding documents to be adopted will be those utilised by the European Union for cooperation projects, adapted for the Sino-Italian development projects financed through soft loan.

    The Bidding Documents to be adopted for Local Competitive Tendering are:

      • Goods, services and works: end-user shall utilize standard bidding documents that comply with MOU. PIU procurement experts will assist end-users and procurement agents if any amendments are to be done to the bidding documents in order to comply with MOU.

    PIU Assistance

    PIU procurement specialists will provide assistance and training to end-users and procurement agents in the preparation and utilization of the bidding documents for projects to be carried out in the environmental sector. PIU's support will focus on verifying the compliance of the bidding documents with MOU and with the principles of transparency, efficiency and economy generally accepted for International Competitive Bidding.

    Bidders Eligibility

    ICT¡¯s are open only to Italian companies or consortia of Italian companies. LCT¡¯s are open only to Chinese companies or consortia of Chinese companies.To avoid any conflict of interest, any expert or firm, including firms within the same legal group, members of consortia and sub-contractors, involved in the preparation of a project must be excluded from participation in tenders or from submitting offers finalised to the implementation of the same project. Bidders will be also requested to comply with the ¡°Anti-mafia¡± regulations in force in Italy.According to each particular project, bidders will be requested to comply with minimum qualification requirements (i.e. economic, financial, professional and technical capacity) in order to assure their successful performance of contracts.

    Bidders are not entitled to bid if they do not comply with the Ethic Clauses of the European Union or if they fall into any Ground for Exclusion (i.e. bankruptcy, res judicata, conflict of interest, fraud, corruption, illegal activity, etc).

    Goods, Services and Works Eligibility

    At least 50% (thirty percent) of the Soft Loan shall be used for purchasing goods and services related to the Programme, which must be of Italian origin; no more than 50% (thirty per cent) of the Soft Loan may be used to purchase local goods, services or works of Chinese origin.

    ¡°Origin¡± means the place where the goods were mined, grown, or produced, or from which the services are supplied. Goods are produced when, through manufacturing, processing, or substantial and major assembly of components, a commercially recognized new product results that is substantially different in basic characteristics or in purpose or utility from its components.

    Procurement Agent Selection

    According to MOU:

      • End-users will be in charge of selecting the Procurement Agent;
      • The selected Procurement Agent must have experience in international bidding;
      • Joint Committee must give its ¡°no-objection¡± to Procurement Agent selection;
      • End-users will bear the costs of the Procurement Agent and by no means shall such costs be paid through the Italian funds.

    The duty of the selected Procurement Agent will be:

      • Collaborating with end-users in the preparation of the Bidding Documents with the support of the PIU Procurement Experts;
      • Carrying out the bidding;
      • Managing, if needed and so requested, the Contract on behalf of end-users;

    Launch of Bidding and Advertising

    International Competitive Bidding:
    According to DGCS standard procedures, end-users must submit the Invitation for Bids (IFB) for publication to DGCS at least 60 days before the intended date of publication. The finalised Bidding Documents must also be submitted to DGCS either at this time or in advance to demonstrate that the proposed IFB corresponds to the objectives of the contract. IFB will be published by DGCS at its own expenses.

    IFB will be published in Italy on:

      • DGCS official bulletin (DIPCO);
      • DGCS website;
      • Italian newspapers;
      • Any other appropriate Italian media if necessary.

    The Invitation for Bids may be published in China by end-users at its own expenses. If published in China, IFB must be in English and must be identical to the IFB published by DGCS.

    Local Competitive Bidding:
    The Bid advertising in China will be carried out by end-users at their own expenses and the Invitation for Bids will be published on. An English copy of the procurement notice shall be submitted to DGCS for "no-objection" at least 30 (thirty) days before the bid advertising.

    Language

    International Competitive Bidding:
    Bidding documents, bids prepared by bidders, as well as all correspondence, documents and reports relating to the bid exchanged by the Procurement Agent and bidders shall be written in English. The Contract and all documents pertaining to the Contract shall all be written in English.

    Local Competitive Bidding:
    The Bidding Documents and bids prepared by bidders, as well as all correspondence, documents and reports relating to the bid exchanged by the Procurement Agent and bidders may be written in Chinese. Before submitting the opening and evaluation reports, the proposals for award and the copies of the Contracts, they shall be translated into English and their costs will be borne by end-users.

    The Contract may be written in Chinese. All correspondence and other documents pertaining to the Contract, which are exchanged by the parties, shall be written in the same language. If the language is Chinese, end-users are required to send to DGCS a certified translation of the successful bid, the evaluation report, the contract and all documents related to the contract.

    Bid and Contract Currency

    Bidders shall quote all the prices in Euro. Contract currency shall be expressed in Euro. Payment to Suppliers under the Contract will be made in Euro.

    DGCS ¡°no-objection¡±

    After contracts are awarded, end-users shall submit the final contract to DGCS for ¡°no-objection¡±. Contracts will enter into force only upon DGCS ¡°no-objection¡±.

    Control Procedures by DGCS

    All authorizations/approvals by DGCS relevant to the procurement activities to be carried out by the End-User and the Procurement Agent will be limited to verify that all procedures and provisions are conducted transparently and efficiently in conformity with the tendering laws and guidelines indicated in the MOU.

    The Evaluation Committee will be responsible to select the suppliers according to the agreed procedures and provisions.
    After the preparation of the Bidding Documents and during the bidding DGCS holds the right to:

      • Designate observer(s) to attend opening session and evaluation sessions. The observer(s) will have no voting rights.
      • Approve the proposal for award and the signed contract.
      • Request, if necessary, a copy of all submitted bids;

    During Contract implementation, DGCS will carry out the following controls:

      • Request, if necessary, all supporting documents relating to the contract;
      • Carry out any necessary checks in case of suspected unusual commercial expenses not mentioned in the main Contract.

    Technical Specifications

    End-users are responsible for the preparation of the Technical Specifications according to the indications prescribed in the bidding documents and the procurement principles indicated in the MOU. PIU procurement experts will support end-users during the preparation and inclusion of the Technical Specifications in the Bidding Documents.